Port St. Joe approves $31,062 change order for Tenth Street work, and 60‑day extension on Roberts & Roberts street contract

3865398 · June 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved a 60‑day contract extension for Roberts & Roberts on a city street project and a $31,062.18 change order to repair Tenth Street between Garrison Avenue and the public works gate; commissioners said the work will support access related to a workforce housing project.

Port St. Joe commissioners on June 17 approved a 60‑day extension for the Roberts & Roberts street project and a change order totaling $31,062.18 to complete repairs on Tenth Street between Garrison Avenue and the public works gate.

Staff reported the original large street project generated a $62,000 credit based on final quantities. The change order would use that credit plus $31,062.18 in city funds to rebuild shoulders, repair a ditch and replace a damaged pipe along Tenth Street, including the stretch adjacent to the Humane Society and the old workshop. Staff said the road is shared by county and city facilities but recommended the city pay to finish the work to support a nearby workforce housing development.

Commissioners approved a 60‑day extension for contract closeout and processing of grant reimbursement and then approved change order number 4 for $31,062.18. Commissioner Kerrigan moved the change order; Commissioner Hoffman seconded. Vote tally was recorded as 4 in favor, motion passed.

Commissioners asked staff to monitor truck traffic on the rebuilt route and consider a “no through trucks” restriction to limit heavy vehicles from cutting through the residential area. Staff said funds to cover the out‑of‑pocket cost are available from an escrowed road fund that is under budget for the year.