Lane water tower expected online by November; contractor change and change order still pending
Summary
City staff said a resident engineer left the project team, a new engineer was assigned and the new Lane water tower could be put into service by November after a weather-dependent lift in July; a change order is expected for earlier contract issues.
Get email alerts on the Water Tower Project topic
No spam. Unsubscribe anytime.
Franklin City received an update on the Lane water tower and associated water-main work, with staff saying the tank should be in service by November and that scheduling the tank lift is weather dependent.
The update matters because the tower will serve parts of the distribution system and earlier contract issues may require change orders that could affect cost and schedule.
Speaker 3, a staff member, said the project's resident engineer is no longer with the engineering firm and a new engineer has been assigned. "I think things are gonna transition smoothly," Speaker 3 said. Staff said the contractor plans to start preparations around July 23 and will need a three-day window of favorable weather to lift and set the tank on the pedestal; after the lift, workers will pour a concrete collar to lock the tank in place. "They'll try to give us a 3 day window for the best estimate," Speaker 3 said.
On financial questions, Speaker 2 asked whether Applied Technologies would absorb costs tied to earlier errors. Speaker 3 said a change order is expected, "Hopefully, by July, we'll have a change order for the whole issue that happened on the first contract." Staff also said there will not be cell antennas on the tower.
Council members asked operational questions including the tank's weight when full and the pedestal design; staff said they will follow up with the contractor for technical details. No council action to alter the project scope or budget was taken at the meeting.