Bowling Green schools: new high school site progressing; 50 of 140 geothermal wells drilled
Summary
At the June 17 Bowling Green City School District board meeting, facilities staff reported progress on the new high school: about 50 of 140 geothermal wells have been drilled, bids for steel and concrete packages are due soon, perimeter fencing and construction trailers are being installed, and the project remains on budget at this date.
At the Bowling Green City School District Board of Education meeting on June 17, 2025, a facilities presenter updated the board and public on construction of the district’s new high school.
The presenter said approximately 50 of the planned 140 vertical geothermal wells had been drilled to date; each well is about 300 feet deep. Two drilling rigs are currently on…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat