Economic and Community Development director reports Rear Main Street construction, Greenwood Pool demolition and master-plan outreach
Summary
Director Stevens updated the Economic and Community Development Committee (reported to the council) on multiple projects: Rear Main Street construction began June 9, Greenwood Pool demolition is under contract and expected this summer, North Central Pathway paving continues through June 27, and the master-plan public engagement continues.
Get email alerts on the Economic Development topic
No spam. Unsubscribe anytime.
At the council's June 16 meeting, Councilor Kacinskas delivered the May Economic and Community Development Committee update summarizing a May 30 presentation by Director Stevens.
Key updates included: construction on Rear Main Street began June 9 (start date noted at the committee meeting); the Greenwood Pool demolition bid was awarded and contractors are assembling bonds and insurance with demolition expected this summer; paving and construction on the North Central Pathway (Crystal Lake Drive connection) is underway with paving continuing through June 27; and the Rome Building demolition was completed in February with a final site walkthrough reported.
Staffing updates included an accepted offer for the assistant director position in Community Development and a posted advertisement for the economic development and finance manager position. Director Stevens also encouraged continued public participation in the city master plan: a public engagement event was held May 22, and the master-plan team is accepting feedback through the city's online engagement portal (search "Gardner master plan").
Councilor Kacinskas asked the council to place the committee update on file; the council unanimously approved the request by roll call. Councilors urged residents to view the recorded committee meeting for more detail.