San Luis awards preconstruction contract for West wastewater plant, approves design change adding reuse pump
Summary
The City of San Luis approved a $339,214.96 preconstruction services agreement with PCL Construction and a $125,470 design change order to add a reuse pumping station and power study to the West Wastewater Treatment Plant expansion.
Get email alerts on the Wastewater Treatment Expansion topic
No spam. Unsubscribe anytime.
The City of San Luis on a unanimous vote approved a preconstruction services agreement with PCL Construction Inc. and separately accepted a design change order to add a reuse pumping station and power-system study to the West Wastewater Treatment Plant expansion.
City public works staff told the council the PCL preconstruction agreement covers the project’s preconstruction design phase and was offered after earlier negotiations with the top-ranked firm failed to yield agreed contract terms. Jorge Perez, assistant director of public works, said, “we began negotiations with the number 1 rank firm… but we couldn't agree on the contract terms,” and that PCL, the next-ranked firm, would proceed with preconstruction work for $339,214.96.
The council also approved change order No. 1 to the design contract with Pacific Advanced Civil Engineering (PACE) for $125,470. Perez said the design now includes a pumping station inside the treatment plant to enable reuse of the plant’s Class A effluent within the facility immediately and to support future off-site reuse such as irrigation; the change order also covers a required electrical power study. Perez noted the design is approximately 90% complete and staff planned a contractor workshop the following week to review that design.
Council members moved and seconded the two measures separately; both motions carried with no recorded nays. The preconstruction agreement and the design change were presented as distinct steps: one secures PCL for preconstruction services, and the other expands the engineering scope already underway with PACE.
Background: city staff said the overall expansion project is ongoing and that selecting a preconstruction services provider and finalizing the design scope are steps toward construction. The reuse pumping station will allow the plant to produce Class A effluent intended for internal reuse and possible future irrigation. Funding sources and longer-term implementation timelines were discussed in general terms during the presentation but were not specified in the motion records.
The council did not amend the contracts during the meeting; both actions were approvals to proceed with the stated amounts.