Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Council hears explanation of rec center change order tied to groundwater and weather delays

3859273 · June 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff explained a change order for the new recreation center covering architectural changes, weather impacts and unexpected groundwater encountered at about 8 feet; council discussion included approval to authorize the mayor to sign change order number 1.

City staff told the council that change order number 1 for the new recreation center covers architectural and engineering revisions, additional work related to recent heavy rain, and remedial work after encountering groundwater at about 8 feet during construction.

Carl, a city project representative, said the contractor required reimbursement for weather-related delays and that drain modifications were needed after the groundwater discovery. The council moved to authorize the mayor to sign change order number 1; staff described the added time as roughly 12 days and explained the scope included drawing changes and additional drainage work.

Why it matters: The change order increases project cost and schedule risk; council authorized the mayor to sign to allow the contractor to proceed with the needed remediation.

Council discussion indicated support with an expectation staff would monitor cost and schedule implications as work continues.