District reports field reconstruction progress, Ken Jenks Auditorium lease extended 6 months
Summary
Superintendent updated the Dennis‑Yarmouth Regional School Committee June 16 on field reconstruction testing and a short lease extension for the Ken Jenks Auditorium; the district is conducting on‑site engineering tests and added a 60‑day termination clause to the auditorium lease.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
Superintendent staff told the Dennis‑Yarmouth Regional School Committee June 16 that field reconstruction work is underway, engineers are conducting on‑site testing, and the district has agreed to a six‑month lease extension with a community group for the Ken Jenks Auditorium that includes a 60‑day termination notice.
On the field project the superintendent said the lower field has been stripped to the base layer and the turf removed; crews will start milling the upper field and removing subbase material this week. Engineers from the project designer and a separate team assisting the district in an ongoing dispute have been on site conducting testing as contractors remove materials. The team will create a roughly 20‑by‑20‑yard test area to evaluate new materials and perform filtration testing before installing materials at scale.
The superintendent said the district is making design tweaks, including higher fence posts, a backstop and installation of a flagpole that had previously been omitted. The work follows a dispute over the original build and the district emphasized additional testing and quality checks to avoid past issues.
Separately, the superintendent reported the district has renewed a lease with a community group for use of the Ken Jenks Auditorium for another six months. The new short-term agreement includes a 60‑day notice clause to terminate the contract, which staff said gives the district more time than a 30‑day notice to rebook the auditorium and to capture revenue while preserving scheduling flexibility. Committee members asked about priority for school performances and why the fee would not be raised for the additional six months; the superintendent said the building retains priority and the district and the group have had a cooperative relationship that supports facility revenue generation.
No formal committee action was required at the meeting; staff said they will continue to provide updates and will consider additional communications to the public about project progress.