Division Road preliminary design advances; stormwater work drives costs and schedule
Summary
Staff reported progress on Division Road preliminary design, including plat updates, appraisals, stormwater modeling tied to floodplain regulations and utility relocations; phase 1 construction is now expected to begin in 2026 with an estimated $1.7–$1.8 million price tag for the first phase.
Village staff briefed trustees on preliminary design progress for Division Road, saying the project remains phased and that stormwater improvements needed to meet floodplain rules are a large share of the projected cost.
Engineering staff said they completed plat updates for multiple parcels to establish right-of-way lines and have begun appraisals and property-owner meetings; appraisers are expected to produce low- or no-value appraisals for some right-of-way areas because much of the land is already used as roadway or drainage.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat