Belton ISD reports near‑completion of 2022 bond projects; Delta facility, punch lists and bus purchases remain
Summary
District staff told the board on June 16 that most 2022 bond construction projects are at or near substantial completion, with punch‑list items remaining at several campuses, anticipated substantial completion for the Delta facility in late July, purchases of 30 buses completed and plans to buy additional vehicles.
Get email alerts on the 2022 Bond Closeout topic
No spam. Unsubscribe anytime.
Belton Independent School District staff told the Board of Trustees on June 16 that the district is closing out most projects funded through the 2022 bond and expects to complete remaining work this summer.
Mike Morgan, who presented the bond update, showed photos of completed spaces in use and outlined a list of active closeouts and remaining work. He told trustees several major renovation/addition projects — at Belton High School, Lake Belton Middle School and Southwest Elementary — are down to a small number of punch‑list items and that district staff expect to complete construction audits and final closeouts soon.
Key points from the update: - Closeouts and savings: Morgan said the bond program has realized buyback and contingency savings that will be returned to the bond program to fund outstanding MEP (mechanical, electrical, plumbing) work and other needs. He reported total GMP (guaranteed maximum price) buyback and remaining contingencies in the program but did not present a single consolidated final closeout total at the meeting. - Hubbard Branch and Southwest Elementary: district staff described deductive change orders and reported additional savings realized in closing out those projects; staff said final auditing and punch‑list work remain before formal acceptance and closure. - Delta facility: after prior schedule delays, Morgan said the contractor had met recent milestones and the district anticipates a substantial completion date of July 27 to allow furniture, equipment and staff moves in time for the 2025–26 school year. - Buses: the district has purchased 30 buses to date (23 regular‑education buses and seven special‑education buses) and expects to purchase roughly 10 more as the program proceeds; buses purchased include three‑point seat belts where required by recent state legislation. - Remaining non‑construction items: MEP/HVAC equipment orders for several campuses are planned; many of the remaining MEP replacements are rooftop exchanges that staff said should be faster to complete once equipment arrives. The district is also moving forward with classroom LED conversions at select campuses.
Morgan said returned GMP savings and interest earnings will be used to complete remaining MEP projects and other bond‑approved items, and he thanked the design and construction partners. Trustees asked about lessons learned from projects that returned savings: Morgan credited competitive subcontractor participation, contractor partnerships and negotiated infrastructure contributions on specific sites for favorable outcomes.
On the consent agenda the board approved multiple items including final payments and closeouts; the consent agenda passed 5-0 during the meeting.