Second-floor courthouse renovation delayed by door-frame and damper deliveries; asbestos work mostly complete
Summary
Kurt, a Samuels Group representative, told the Trempealeau County Property Committee on June 9, 2025, that demolition and asbestos abatement on the county building’s second floor are largely complete but that two long-lead items — door frames and fire dampers — are delayed and expected to arrive this week or next, creating a “couple of weeks” slip for parts of the phase.
Kurt, a Samuels Group representative, told the Trempealeau County Property Committee on June 9, 2025, that demolition and asbestos abatement on the county building’s second floor are largely complete but that two long-lead items — door frames and fire dampers — are delayed and expected to arrive this week or next, creating a “couple of weeks” slip for parts of the phase.
The update matters because those delayed components affect the planned sequencing of work and moves into the renovated spaces, Kurt said: “For the most part the demolition is done. The asbestos abatement on that Second Floor is mostly done. The the 2 lead time items that we're waiting on are some door frames and some fire dampers. We are told that we should get those deliveries this week and some into next week.”
Committee members and county maintenance staff described which areas are affected and how the schedule may shift. Kurt said the delayed deliveries mainly…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat