IMS renovation: asbestos find slows music-suite demolition; auditorium and gym upgrades continue
Summary
Contractor Site Logic updated the Bethel Park School District board on phase 3 of the IMS renovation, reporting an asbestos discovery in the music suite, continued auditorium lighting and sound work, gym bleacher demolition, roof setbacks and near-term grant paperwork to secure $1.7 million in Act 34 funds.
Site Logic, the contractor on the IMS renovation, told the Bethel Park School District Board that the project remains active but has encountered a localized asbestos finding in the music suite that has delayed full demolition there.
The contractor said crews completed demolition in most of the music area but “found there were 2 layers of flooring, and underneath there was some asbestos flooring that we were unaware of.” The firm said it is awaiting the 10-day county notice required before completing miscellaneous demolition in that room and will proceed with drywall and other finishes after inspections…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat