Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Streets Infrastructure topic

No spam. Unsubscribe anytime.

La Porte board approves change order for Indiana Avenue sewer and water work; wastewater portion $151,586

3853640 · June 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a change order to Indiana Avenue construction, adding a $151,585.69 wastewater connection and $10,086.10 for water work to improve storm connections and enable future sewer separation; members said the project remains under original budget estimates.

The La Porte Board of Public Works and Safety approved a change order Wednesday for Indiana Avenue construction that adds new storm and utility connections and shifts a problematic connection away from an older brick alley sewer.

Jerry Jackson, wastewater, said the largest item in the change order is a $151,585.69 wastewater expenditure — about 7.7% of the original contract — for deeper connections and to take storm flow out of a failing brick sewer and tie it into a larger concrete sewer. The water portion of the change order is $10,086.10 (about 3.2% of the contract) to reconfigure connections at Kingsbury Avenue to allow a future extension.

Why it matters: The change order addresses a recently discovered deficient storm connection and a collapsed brick sewer south of Lincoln Way. Jackson said moving the storm connection to the larger Lincoln Way concrete sewer is a more appropriate long-term solution.

Board members noted the project remains below the original estimated budget. Jackson said the city had budgeted $2.3 million and that bids had come in near $1.9 million; with this change order, the project cost remains several hundred thousand dollars under the original estimate. Board members also discussed construction schedule items and groundwater/dewatering issues that had slowed progress.

The board approved the change order after engineering and INDOT review, and members said the work will support future sewer-separation projects and safer stormwater routing.