Board authorizes change order adding $80.57 to Johnson Avenue sidewalk project
Summary
The Board of Public Works and Safety approved change order No. 1 for the Johnson Avenue sidewalk project. The change order covered design adjustments (a vertical curve and thicker sidewalk at drive approaches) and increased the contract by $80.57; the board authorized the mayor to sign.
Get email alerts on the Sidewalk Infrastructure topic
No spam. Unsubscribe anytime.
The Franklin Board of Public Works and Safety on June 16 approved change order No. 1 for the Johnson Avenue sidewalk project, a final balancing item that increased the contract by $80.57 and authorized the mayor to sign the change order on the board's behalf.
City staff explained the change order combined added items required to complete the work: a vertical curve where the sidewalk meets the roadway, thicker sidewalk at driveway crossings and slight adjustments to sidewalk limits. After balancing these items, staff said the net increase from the original contract sum is $80.57.
Board members praised the contractor's work on this and other recent sidewalk assignments. The contractor that completed the work was identified in discussion as All Star Paving.
A motion to approve change order No. 1 and to authorize the mayor to sign on behalf of the board was made, seconded and approved by voice vote.
Ending: The board's approval completes the final change-order process for the Johnson Avenue sidewalk project; staff will execute the change order and finalize contract closeout.