Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Ct Center Construction topic

No spam. Unsubscribe anytime.

Bismarck schools report CT Center construction progress; foundation seeks sponsor for remaining phase

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported that construction work at the CT Center is underway (sheetrock, concrete and exterior panels) and that the BPS foundation is pursuing a major sponsor to fund remaining phase-1 mezzanines; the board was informed a fundraising campaign will begin this summer.

At the June 9 Bismarck Public School Board meeting, district staff updated members on construction and fundraising for the CT Center, the district's single major capital project.

Mr. Sherry, who presented the update, said "sheetrock is happening and concrete is being finalized," and that exterior wall panels on the north shelled portion are in place. He told the board the project still has a funding gap covering structural steel mezzanines that would complete part of phase 1.

Mr. Sherry said the BPS Foundation has a promising lead with a potential major sponsor and that the district plans to launch a fundraising campaign this summer, followed by outreach to community partners. Superintendent Dr. Fosnott added that bringing donors into the finished structure helps prospective supporters "see the space" and understand why they are supporting students.

No formal board action was taken on the project update during the meeting; staff included financial information in their materials and said they would return to the board for consideration if additional funding or contract decisions became necessary.