Commissioners approve $92,262 change order for Atascosa County sheriff’s office renovation

3846961 · May 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commissioners court approved a $92,262 change order—covering cabling and alternate parking—for the Atascosa County Sheriff’s Office addition and renovation project; the project remains funded by ARPA and the change is within allowable limits.

The Atascosa County Commissioners Court approved a $92,262 change order for the Sheriff’s Office addition and renovations during a special call meeting. The work includes $34,485 for cabling and $57,007.77 for alternate parking, which together total $92,262 on the change order.

Tracy Barrera, county auditor, told the court the original construction contract for the project was awarded to Integrity Contractors Incorporated on Dec. 23, 2024, for $1,067,777 using ARPA funds. Barrera said the change order keeps the total project cost within the dedicated ARPA allocation and is within the allowed change‑order cap.

Why it matters: the change order increases the project total but, according to the auditor, remains within budget authority established for the renovation. Commissioners approved moving forward with the change orders by motion and recorded votes.

The motion to accept the change orders was made by Commissioner Riley and seconded by Commissioner Pavelic. The court recorded votes in favor from Commissioner Bowen, Commissioner Pavelic and Commissioner Riley; Commissioner Gillespie was absent.

Barrera explained the alternate parking was an alternate bid included in the bidding process and that she separated the line items to explain the total of $92,262. No amendments, postponements or further study directions were recorded on the change‑order item during the meeting.