Board approves paving contract revisions requiring board approval for major change orders
Summary
The school board approved revisions to the district's paving contract: replacing the named owner's representative, setting liquidated damages at $1,250 per day, and requiring board approval for change orders that increase contract sum or scope.
Get email alerts on the Contracts Procurement topic
No spam. Unsubscribe anytime.
The Jackson-Madison County School Board approved revisions to the district’s paving contract that change the owner’s representative, set liquidated damages at $1,250 per calendar day, and require board approval for any change order that increases the contract sum or significantly changes the scope of work.
A board member moved to approve the contract with three specific revisions: change the owner’s representative from Joe Albright to “a person designated by Dr. King,” revise the liquidated-damages provision to $1,250 per calendar day, and amend general conditions to require board approval for change orders that raise the contract sum or significantly alter scope.
Staff explained the changes were recommended after a recent work session and that Joe Albright “will not be with us past June,” so he cannot remain the owner’s representative on the project. Staff also said the liquidated-damages language in one section conflicted with the standard form and should be aligned to $1,250.
Board members asked for comments; none were raised that altered the motion. The board approved the contract revisions by voice vote.
The motion also added a provision to ensure the board retains final approval over changes that would increase the project cost or materially change the work, and staff said the change-order clause is intended to protect the district’s fund balance and oversight.