Oshkosh school district lays out Phase 2 construction, West Side boundary timeline; Traeger set to go to bid in September
Summary
District staff presented the Phase 2 facilities progress report and an online packet detailing school closures, boundary changes and project timelines. Traeger Elementary is on track to be bid in September; Shapiro and Roosevelt are scheduled to close in 2026–27 and 2027 respectively as part of a multi‑year consolidation plan.
The Oshkosh Area School District presented a Phase 2 facilities progress report on June 11, outlining timelines for school closings, boundary changes on the West Side and major construction projects tied to the 2025 referendum.
District administrator Conrad Peters told the board the Traeger Elementary project is “approaching the point where we are going to be ready to bid the Traeger Elementary Project in September.” She directed members to a phase‑2 page on the district website that includes monthly progress reports, project tiles (new middle school, elementary expansions, a pre‑K center and air conditioning), and an infographic showing a year‑by‑year boundary timeline through 2029.
The timeline Peters…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat