Columbia City public works reports failed bacteria test, force-main repairs and sludge-hauling planning
Summary
Public works reported a failed initial bacteria test on a new water main on North Park Drive, sinkholes and a leaking water line tied to the force-main project, and that sludge-hauling plans and landfill-permit samples are underway.
Get email alerts on the Water Sewer Infrastructure topic
No spam. Unsubscribe anytime.
Columbia City public works told the Works and Safety Committee on June 10 that a first bacteria test on a newly laid 6-inch main on North Park Drive did not pass and a follow-up sample was taken the same day.
Public works said it expects to receive results from the second test; if it does not pass, crews will re-chlorinate the line and repeat testing. The department said passing two successive bacteriological tests is required before connecting homes to the newly laid main.
Separately, the force-main project was inspected and staff identified a few sinkholes that need repair and a leaking water line on East Jefferson that requires repair. A seating issue around an air-release valve (ARV) at 901 East Jefferson also needs correction; staff told a contractor that the city will not accept the contractor’s final payment request until those repairs are complete.
Public works said samples have been submitted as part of a landfill-permit application for sludge hauling; no start date for sludge hauling has been set. Staff reported they are adjusting treatment procedures to address high sludge inventory and will implement changes gradually.
The committee did not take a formal vote on these operational items; staff characterized most items as ongoing repairs and operational adjustments and said they will withhold final contractor payments until identified deficiencies are corrected.