Committee advances $2.49 million agreement with WSDOT to replace fish-blocking culvert on Sexton Creek
Summary
The committee moved Motion 20-45-23 to the general session for consent to authorize up to $2,487,917.90 to WSDOT for work on a county-owned culvert at Sexton Road to remove a fish barrier on Sexton Creek and coordinate upstream improvements under US 2.
Get email alerts on the Fish Passage Culvert Replacement topic
No spam. Unsubscribe anytime.
The Snohomish County Planning and Community Development Committee moved Motion 20-45-23 to the General Legislative Session for consideration on the consent agenda to approve an agreement with the Washington State Department of Transportation.
County staff said the agreement (GCB 4,099) would authorize WSDOT to perform work on a county-owned culvert under Sexton Road and that the county will pay up to $2,487,917.90 for work in county right-of-way. The work would replace the county culvert with a fish-passable structure; WSDOT is separately planning work on a nearby culvert under U.S. 2 that currently would become the next upstream barrier.
Staff said the two agencies coordinated design development so the combined projects will open Sexton Creek and connected Pilchuck River habitat to fish. The stated funding sources are federal and state grants, including National Oceanic and Atmospheric Administration funds and a State Fish Barrier Removal Board grant. County staff told the committee the listed grant money has been allocated and no adjustments to the county budget or grant work plan were necessary. The $2.49 million figure includes a 30% contingency.
Surface Water Management asked for urgent handling to meet contractual timetables; the committee moved the motion to the Jan. 8 General Legislative Session consent agenda for consideration.