The Iroquois County Highway Committee voted to forward a $745,825 bid from IPC for Bridge 2800 North to the full county board, and members amended the motion to specify a multi-party funding split. The committee’s record contains multiple, inconsistent county-share figures discussed during the meeting.
Get email alerts on the Transportation Bridges topic
No spam. Unsubscribe anytime.
The Iroquois County Highway Committee on June 2 voted to forward a $745,825 bid from IPC for repairs at Bridge 2800 North to the full county board, and members amended the motion to specify how the project will be funded.
The motion, as restated during the meeting, identified an amended county share for the bridge work and a split of the remaining cost among township and bridge funds. Members discussed several figures on the record; the chair corrected a county-portion figure during debate and the committee approved the amended funding breakdown and forwarding action.
The bid amount under consideration was $745,825. Committee discussion recorded two different county-portion figures during the meeting: $216,274.86 as part of an amendment and later a corrected figure of $216,002.74. Separately in the committee record, staff read a further funding breakdown that listed a TVP fund contribution of $173,019.89, a county-bridge contribution of $21,627.49, and two townships each paying $10,813.74. Committee members said the final motion would separate the county portion from other funds and allocate the balance across township/bridge funding, summarized in the meeting as an 80/10/10 split (80% township bridge fund, 10% county bridge, remaining split between two townships).
Committee members emphasized procedural clarity. One member urged careful wording of motions so the record would match the committee’s intent and the action going forward. The minutes and discussion indicate the committee’s role was to forward the bid and funding recommendation for formal approval by the full county board rather than to finally award the contract.
The committee approved the motion to forward the IPC bid, including the amended funding split, by voice/roll call vote. Several committee members voiced assent during the roll call.
The county engineer and highway staff will prepare the forwarding packet for the county board, which will take the final vote and authorize awarding the contract if it approves the funding arrangement.
Details that remain on the record: (1) the bid total of $745,825; (2) the committee amendment specifying a county portion that was verbally corrected during the meeting (two different county-portion figures appear in the transcript); and (3) a final allocation framework described during the meeting (township/TVP/county split). The committee did not itself authorize contract award — it forwarded the bid package to the county board for formal action.
The county board will consider the packet and the funding allocations at a later meeting; the highway committee’s action was to forward the bid with the committee’s recommended funding split.