Commissioners approve $4.87 million Northwest Florida Water Management grant amendment and related work orders for Indian Springs sewer project
Summary
Jackson County approved Grant Amendment No. 4 from the Northwest Florida Water Management District to increase funding by $4,872,714 and authorized associated change orders and work authorizations for phases of the Indian Springs sewer project, including design work and construction change orders to add phase 2D into the existing contract.
Get email alerts on the Infrastructure Sewer Project topic
No spam. Unsubscribe anytime.
Jackson County commissioners approved a $4,872,714 amendment to a Northwest Florida Water Management District (NWFWMD) grant and authorized associated change orders and work authorizations for the Indian Springs sewer project.
Staff described Amendment No. 4 as adding $4,872,714 to Grant No. 2036 and extending the grant schedule by 365 days. The funding will support construction and design for multiple project phases; staff said work will include design for Seminole Drive (phase 2E), construction tasks for phases 2C and 2D, and rehabilitation of a pumping station.
The board also approved a change order to incorporate phase 2D construction into the existing contract for phase 2C rather than rebidding the work. Staff said the contractor for 2C is already on site, the unit prices were locked in two years ago, and adding 2D under change order would likely be less expensive than a new competitive bid. A roughly $2.8 million change‑order figure for phase 2D was discussed during the meeting; staff and legal said the work authorizations and change orders comport with grant conditions and county purchasing policies.
Commissioners asked about fairness to other bidders and whether change orders might unreasonably expand a single contractor’s work beyond the original low bid. Staff and legal responded that the funding agency (NWFWMD) approved the approach, the pricing is unit‑based and was established in the original contract, and purchasing and legal found the procurement acceptable. One staff member noted certain future phases would still be competitively bid, including Blue Springs where lift stations are involved.
The board voted to approve the grant amendment, the listed change orders, and multiple work authorizations for design and construction tied to the NWFWMD funding.
What’s next: Staff will execute the grant amendment, issue the approved work authorizations, and manage construction under the amended grant schedule.