City accepts South Bernard reconstruction as substantially complete; project 1% over budget

3780884 · May 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff recommended acceptance of South Bernard reconstruction as substantially complete; the project finished with a final contract amount about 1% over the original budget, with remaining funds to cover punch-list items and fees.

The City of Broussard moved to accept the South Bernard reconstruction project as substantially complete at its May 27 meeting, following a presentation from Joseph Marino of project consultant DDG.

Marino told the council South Bernard, between Main Street and U.S. 90, is open and that remaining punch-list items should be finished within weeks. He reported the final contract amount was $4,242,668.59, about $43,636.59 over the original contract of $4,000,199.32 — roughly a 1% overrun attributable to unforeseen conditions including conflict boxes and unstable subgrade that required ripping, replacement and chemical treatment.

Why it matters: The reconstruction widened lanes, added a new bridge, enclosed ditches and improved safety on a roadway used by heavy truck traffic and access to Leeta Park and other businesses.

Details from the meeting: - Marino said remaining funds included a project funding balance of $459,628 and ~$431,266 due to the contractor, leaving about $28,000 available after contractor payment; incidental consultant and inspection fees of about $5,000 could be absorbed within that balance. - The work was funded primarily by Capital Outlay; Broussard initially advanced matching funds and was expected to be reimbursed by Capital Outlay funding. - Marino described tangible improvements: three travel lanes, a new wider bridge, and closed-in ditches to address safety concerns.

Discussion vs. decision: Council voted to approve the substantial completion recommendation (motion approved). Marino and staff said paperwork will follow to enable the mayor to sign the substantial completion certificate once punch-list items are closed.

Next steps: Contractor to complete punch-list items in the coming weeks; the mayor will sign the substantial completion certificate and final pay processes will be completed pending confirmation from the facility planning manager.