Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Fy26 Budget topic
No spam. Unsubscribe anytime.
CFC reviews preliminary FY26 budget: $108M revenue plan, heavy capital spending and special‑education cost growth
Summary
Committee examined the district’s preliminary fiscal 2026 budget showing $108 million in budgeted revenues, roughly $62 million for capital projects, planned transfers of about $44 million from operating funds to capital and an estimated $1.6 million increase in special education outplacement costs.
Get email alerts on the Fy26 Budget topic
No spam. Unsubscribe anytime.
Oak Park–River Forest SD 200’s Community Finance Committee on June 10 received a preliminary review of the district’s fiscal year 2026 budget, in which staff presented a $108 million revenue plan, heavy capital spending for ongoing construction and a projected increase in special‑education costs.
The finance presentation showed $108,000,000 in budgeted revenue for FY26 and roughly $62,000,000 (about 40% of the total budget) earmarked for capital expenditures tied to ongoing projects, including Project 2 and the conclusion of geothermal work. Staff said a portion of capital spending will be paid from remaining debt certificate proceeds and interest; the budget assumes about $28,000,000 of construction expense covered by those proceeds and earned interest, and about $41,000,000 coming from operating‑fund transfers.
Ryan (district finance staff) told the committee the education (operating) fund will transfer just over $22,000,000 to capital in FY26. After projected transfers, the operating fund balance is budgeted to end FY26 at roughly $30,000,000 — a fund‑balance‑to‑expenditures ratio of about 32%, which the presenter said sits within the district’s 25%–50% policy target.
Revenue details highlighted several drivers and risks: property taxes are the largest source and the levy adopted last December provided a 2.5% increase plus new property; corporate personal property replacement tax (CPPRT) receipts have fallen sharply since the pandemic and the budget assumes a further decline (the presentation built in a 17% decrease for CPPRT in FY26); interest earnings are expected to produce about $3.8 million next year; and a $3.5 million state capital grant associated with the Imagine Foundation’s $12.5 million commitment to Project 2 is budgeted for part of FY26 with additional reimbursements expected the following year.
On expenditures, salaries were budgeted for a 4% increase overall; benefits used an 8% assumption for health insurance (staff noted calendar‑year timing makes the benefit line more volatile). Equipment spending is reduced by more than $500,000 from the prior year, and electricity costs were called out as a material increase — roughly $225,000 — driven by transmission and procurement factors outside district control.
Special education was a key area of concern: staff estimated students placed in private special‑education programs could rise from 46 to 55 at an average cost of about $80,000 per student and residential placements could increase by two students at about $200,000 each. Staff estimated the combined special‑education impact at about $1,600,000 in FY26. Presenters said some outplacement counts are still being evaluated over the summer and that federal and state reimbursement rates for portions of those costs are variable; historically, federal reimbursement has covered a substantial share of room‑and‑board in outplaced placements but state categorical reimbursements can lag or be held flat.
Project‑specific numbers included an estimated $10,000,000 of remaining Project 2 expenses after FY26; staff said that gap would be covered by a mix of the Imagine Foundation donations, state capital grant reimbursements and a further transfer planned in FY27.
The presenter also noted timing risks: potential Cook County delays in property tax billing could reduce interest income and affect cash flow; staff built a two‑month delay into cash‑flow assumptions. Committee members asked for continued monthly or near‑term updates on the construction budget and requested a brief construction status at the August meeting. One staff member told the committee the construction dashboard available on the district website currently shows Project 2 as on budget and on schedule.
Ending: Staff will refine assumptions and update the five‑year financial projection during the summer; the board will review a more complete budget in August, hold a public hearing in September and adopt a final budget later in the fall.

