Sydney’s solar farm reported operational; initial output near guaranteed level
Summary
City staff reported the new solar farm began operations June 3 with a certificate of operation; staff said the array is rated at 3,800 kilowatts and initial output has been about 91 percent of guaranteed production.
Get email alerts on the Solar Energy topic
No spam. Unsubscribe anytime.
City staff reported on June 10 that the municipal solar farm is operational. The project received a certificate of operation on June 3, staff said, and early performance data show output at roughly 91 percent of the guaranteed capacity.
City staff member Josh told the council the solar farm has a rated capacity of 3,800 kilowatts. The council asked staff to include metering information in a future meeting so the council can track kilowatt-hour production and compare it to guarantees and expected output. Staff said they will return with meter-read data at the next meeting for a more complete monthly average.
Councilmembers welcomed the update and noted no major operational issues had been reported in the days since the certificate of operation was issued.