Waynesville board gets construction update; approves $36.25 million Wright contract after $10.7 million reduction
Summary
District staff told the Waynesville R‑VI Board of Education that Liberty Elementary excavation is ahead of schedule, solar panel work will be bid this summer, and high‑school HVAC work is near completion; the board approved a change order that reduced Wright Construction's Liberty Phase 2 contract by $10,727,078 to $36,247,922.
Mr. Harrison, a district staff member, updated the Waynesville R‑VI Board of Education on multiple campus construction projects and the board approved a large change order related to Liberty Elementary.
The update covered Liberty Elementary, where major excavation is “expected to be complete in July of ’25,” retaining walls are scheduled to finish in February 2026 and phase 2 work by Wright Construction will begin when the contractor mobilizes in August; Mr. Harrison said the district remains on track for a March 2027 substantial-completion date. He also said the district plans to bid a solar-panel…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat