Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Navasota staff report delays on pump and tank work; council approves change order for wastewater repairs

3749172 · June 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported weather delays to several water projects and identified erosion at Cedar Creek; the council approved a change order not to exceed $15,000 to repair a cracked sewer line under the wastewater plant lab slab.

City staff told the Navasota City Council that several capital projects are delayed because of weather and contractor scheduling, and the council authorized a change order to repair a sewer line discovered beneath the wastewater treatment plant lab.

Project manager Matthew Dooling said the Waterway Number 8 pump installation was postponed after heavy rain prevented contractors from getting rigging into the well site; Elevated Storage Tank Number 3 was delayed by a contractor conflict but staff expects mobilization within one to…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans