Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Diversion project hits construction milestones; inlet gates commissioned and channel excavation passes 34 million cubic yards

3736324 · May 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported gate machinery for the diversion inlet was commissioned, multiple bridge and deck pours are underway, channel excavation has moved more than 34.5 million of an estimated 45 million cubic yards, and environmental work (tree planting, cultural monitoring, mussel and fish salvage planning) is ongoing.

Board members received a broad construction and environmental compliance update, including recent commissioning, bridge milestones, channel excavation totals and habitat‑salvage planning.

“The gate machinery went through commissioning, and everything went really well. Everything's working as intended, and we have gates that raise and lower properly,” said Terry, a staff member delivering the construction update on the diversion inlet. Terry said final inspections and training are upcoming at the diversion inlet and the Wild Rice River…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans