Summary

Mayor Scott James said crews have been running piping from the Highland Drive tower to a new tank near City Park and expect work to finish around August or September, though rock has slowed work in places.

Mayor Scott James said work on a new water tower near City Park is progressing and that crews have installed piping from the tower on Highland Drive down to the new tank and toward Canal Terrace.

“Yeah. They've made a lot of progress. They've ran, piping from, I believe, the tower up on Highland Drive down to the new tower on the backside of Scout Hill there in City Park. Mhmm. And, they've started running piping down towards Canal Terrace to tie into the main waterline,” James said on the podcast.

Why it matters: the infrastructure project is intended to improve water service reliability across parts of St. Albans and may cause temporary traffic and access disruptions.

James estimated completion “sometime in August or September,” adding “Could be a little bit later” because crews “run into rock” in some sections. He thanked residents for patience as intermittent road closures have occurred while crews lay pipe.

Ending: City staff said they will continue to monitor progress and provide updates; no final completion date or construction cost was provided on the podcast.