County approves $20,118 contingency use for Karst Athletic Complex equipment and storm fitting

3707830 · June 8, 2025

Summary

Commissioners approved Change Order No. 5 to Reed & Sons Construction Contract No. 1 for the Karst Athletic Complex Improvement Project to allocate $20,118.15 from contingency funds for an equipment garage, electric, stone gate and storm fitting; the contract amount was not increased beyond contingency.

The Monroe County Board of Commissioners on June 5 approved Change Order No. 5 for Reed & Sons Construction, authorizing use of $20,118.15 from the project contingency for the Karst Athletic Complex Improvement Project to cover an equipment garage, electrical work, a stone gate and a storm fitting.

Parks Director Ms. Whitmer told commissioners the change order does not increase the contract value beyond the existing contingency and that the $20,118.15 will be spent from contingency funds already in the contract.

Commissioners and the parks director noted public anticipation for the complex and apologized for construction traffic; the Board approved the change order by roll call vote 3–0.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source