The Hortonville Village Board approved payment of $295,768.41 to Vinton Construction for completed work on the Alonzo Park playground and splash pad, holding a portion of the contract pending grass establishment.
The Hortonville Village Board on June 5 approved payment of $295,768.41 to Vinton Construction for work completed at Alonzo Park, including the village's new playground and splash pad.
Board members voted to release the majority of pay application number 3 while retaining a portion of the contract amount until landscaping — primarily grass seed — has established. The board discussed that the holdback is intended to ensure final site restoration is complete before full payment.
Village staff said most construction work included in pay application 3 is finished and that the contractor is completing final punch-list items. The payment was presented after a site review with the village's consultant; the board asked that the remaining retainage be held until grass growth is confirmed.
Trustees moved and seconded the payment; a roll-call vote carried the motion. The approved amount on the record is $295,768.41 and the contractor name is Vinton Construction.
The payment completes a major milestone on the Alonzo Park project. The board discussed remaining warranty and site-restoration items to be monitored by staff and the village consultant before final closeout.