Louisa County schools report addition nearly complete, project 73% done and on budget
Summary
District staff told the school board the addition’s roof is 95% complete, 73.47% of work is finished and $15,675,979.40 has been spent (60.3% of the project budget); staff said the project remains on schedule for opening before school starts and the district reported one small change order related to irrigation power.
Staff member A, a staff member, told the Louisa County Public Schools Board the addition and associated work remain on schedule and on budget.
“The roof is 95% complete,” Staff member A said. “We have currently spent $15,675,979.40 on the addition project. That represents 60.3% of our budget is spent. We have completed 73.47%.”
Board members were shown photographs and a progress report that, according to staff, show rooftop equipment installation, classroom finishing, ceiling-grid installation and retrofitting of existing rooms into science classrooms. Staff member A described openings…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat