Cheltenham SD outlines timelines, cost changes for Glenside and Cedarbrook additions and high school work
Summary
District staff briefed the facilities committee on construction schedules: a high-school partial roof project will run June 23–Aug. 17; athletic-stadium demolition has begun; Glenside addition is on a permitting track with a reduced estimate; Cedarbrook has added scope and a higher budget and may require bond issuance.
Mister Snyder, a district staff member presenting construction updates, told the facilities committee the high school partial-roof replacement is scheduled to begin June 23 with anticipated completion Aug. 17, and that the contractor will use part of the parking lot through the summer.
Snyder said demolition and mobilization for athletic stadium work are starting this week and that more on-site activity is expected in coming days. On the Glenside Elementary addition, he said the district has completed the township land-development steps and is tracking required approvals from the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat