Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Site Plan Amendment topic
No spam. Unsubscribe anytime.
Commission approves amended Kaufman Robinson site plan in Bonfire subdivision after height increase explained
Summary
The commission approved an amended site development plan for Kaufman Robinson Inc. on Lots 1 and 2 of the Bonfire Subdivision, accepting a height increase from 28 to 37 feet (above the 10% amendment threshold) while requiring a lot‑line adjustment before final acceptance.
Get email alerts on the Site Plan Amendment topic
No spam. Unsubscribe anytime.
The Wellington Town Planning Commission approved an amended site development plan for Kaufman Robinson Inc.’s proposed industrial building on Lots 1 and 2 of the Bonfire Subdivision Filing 2, including a requested increase in building height from 28 to 37 feet.
Planner Aidan Checkett told commissioners the site plan was previously approved by the commission on Nov. 7, 2022, and that site plan approvals are valid for three years. He said the applicant returned because the change in building height exceeds a land‑use code threshold requiring commission review; Checkett described other changes to landscaping, parking and illumination as minor and below the 10% threshold.
Checkett said the proposed structure is a large industrial building on lots within the existing light‑industrial Bonfire Subdivision and that the highest point on the building is now 37 feet, which remains 8 feet below the maximum allowed in the zoning district. He also said a lot‑line adjustment is required before the town will accept the site plan for final administrative approval.
Applicant representatives and the project team attended the meeting. Horacio, speaking for the applicant team, explained the reason for the height increase: the owner needs a 14‑foot clear fabrication area and additional space for docks, electrical and HVAC infrastructure and a partial second floor. "It was their equipment clearances mainly. Interior clearances," Horacio said.
Staff told the commission the total number of parking spaces remains the same and meets town standards, that minor landscaping adjustments remain compliant, and that the commission previously allowed flexibility on screening along the east lot line where the site faces another industrial property. Checkett said engineering staff found only minor labeling and terminology comments.
Because site plan review does not require a public hearing, the commission moved and approved the amended site development plan with the staff’s conditions. Commissioners adopted the staff findings for approval; the motion passed on roll call.
Next steps: the applicant will process the required lot‑line adjustment and address minor planning and engineering comments before the town issues final acceptance of the amended site plan.