Village updates: Eastern Avenue bid opening, culvert work, Baker Road lights to be energized
Summary
Village staff told trustees two box culverts are complete, a 4-inch binder will be placed on the repaired road to allow temporary opening, and the bid opening for the remainder of Eastern Avenue is set for June 26 with award planned at the July 1 meeting and a completion date targeted for September.
Village staff provided progress updates on several road and infrastructure projects and gave schedule guidance to the Board of Trustees.
John (staff) reported two box culverts have been installed. He said crews will place a 4-inch binder so the road can be opened while the full reconstruction…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat