Council approves two change orders as Virginia’s new public safety facility nears completion
Summary
City staff reported construction milestones, a remaining owner contingency of about $662,000 and recommended two change orders — one for fire training anchor points and another to add welding exhaust in a tool room; both passed the Committee of the Whole.
Contractors and city project staff told the committee Tuesday the new Virginia public safety facility is nearing completion, with exterior work, interior finishes and roofing largely finished and occupancy and move‑in planned this fall.
“Projects on schedule, under budget, in really good shape overall,” Carl Sanderson project manager Sean Lewis told the council, citing site work, acoustic ceilings, tile installation and plumbing fixtures in progress and an overall project footprint of about 50,000 square feet.
Budget and change orders: Lewis presented a budget…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat