Geneva awards $535,685 water‑main replacement contract at Del Norte Health and Wellness Center with 10% contingency
Summary
The Committee of the Whole approved a low bid from Fox Excavating to replace a deteriorating water main at the Del Norte Health and Wellness Center for $535,685.40, with a 10% contingency raising the not-to-exceed amount to $589,253.94; staff said the main, installed in 1988, is failing due to corrosive soils and will be replaced with PVC C‑900.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
The Geneva Committee of the Whole approved a contract with Fox Excavating for water-main replacement at the Del Norte Health and Wellness Center in the low-bid amount of $535,685.40, with a 10% contingency authorizing change orders up to a not-to-exceed total of $589,253.94.
Staff said the FY26 budget contains funds for the project. Superintendent Van Gescombe explained the existing water main was installed in 1988 and has been deteriorating rapidly in that location due to corrosive soils; the city recommended replacement with PVC C-900 pipe to avoid soil-related corrosion.
Alderson Kasarach asked about the pipe material and was told the PVC C-900 product will not be affected by the corrosive soils. Alderson Perzmolecki asked whether the work expands service; staff said this is primarily a straight replacement and not an expansion of the service area.
The Committee adopted the resolution by voice vote; staff said the work will be coordinated with the campus owner (hospital) when needed. The contract includes a contingency to account for unforeseen field conditions.