Council approves Eldridge Park Estates special permit after debate over stormwater rules; mayor votes no
Summary
Council approved a special permit for Eldridge Park Estates but the item drew debate about whether the development should meet the newer stormwater rules after its previous site plan expired; the mayor voted no and the motion passed 4-1.
Get email alerts on the Stormwater Development topic
No spam. Unsubscribe anytime.
The Town of Davie council on June 3 approved a special permit for Eldridge Park Estates after a contested discussion about on-site stormwater retention rules for residential developments.
Mayor Paul told colleagues he pulled the site plan to explain his opposition, saying the town had changed its drainage code to require developments to "hold their own water" and to avoid placing retention on residential property. He said nearby streets had begun to flood after new homes were built and that the council should not set a precedent of approving developments that place retention on residential lots.
Applicant representatives, including Jason Wilson of Pillar Consultants, said the project had previously been approved but the site plan lapsed because the contractor failed to complete permit payments; they said they had restarted the permitting process, worked through permitting requirements with the town and regulators, and had increased on-site storage by approximately 59% compared with the earlier design. Wilson said the applicant also committed to cleaning out the adjacent street drainage system on Southwest 26th to the canal to reduce flood risk.
Council members debated whether the prior approval and the project's limited size (five lots on roughly five acres) justified permitting the design under the older standards or whether the developer should comply with the updated code. One council member said that although they agreed with the code change in principle, the project's prior negotiation and the improvements made during re-submittal supported approval.
The council approved the special permit on roll call; Mayor Paul voted "no." The recorded roll call showed the motion passed with four "yes" votes and one "no." Staff and the applicant said drainage-district comments had been addressed and that the revised design provided additional storage and a small knee wall along the southern property line.
Why it matters: The vote highlights how the town implements updated stormwater standards when previously approved projects lapse, and it signals the council's judgment about exceptions for small infill projects where applicants say they have improved drainage design.
Next steps: Staff will process final permits and the applicant will proceed with required drainage work, including the street cleaning and the additional on-site storage described by the applicant.