Hot Springs board approves multiple change orders, discusses transformer delay at Davidson Drive wastewater project
Summary
The Hot Springs Board of Directors approved several contract change orders tied to the city’s wastewater bond projects and heard city staff say a delayed utility transformer from Entergy could push final state closeout to mid-2026 despite temporary power allowing station operations earlier.
The Hot Springs Board of Directors on June 3 approved a series of change orders and heard updates on major wastewater projects bankrolled by the 2025 wastewater bond fund, including work at the Davidson Drive wastewater treatment plant and the Gulpha (Guilpha) Wet Weather Pump Station.
City Manager Bill Burrow told the board the city currently has about $34.5 million in active projects at the Davidson Drive plant and outlined a slate of related contracts and upcoming work. Engineering project manager Todd Pillar told directors that the Lower Gulpha (Guilpha) interceptor work and other force-main and interceptor contracts remain underway and that one contractor’s negotiated change order produced a $1,281,276 cost reduction.
Why it matters: These projects are part of a previously disclosed consent administrative order and the city’s wastewater bond program; changes to scope, schedule or cost affect when the city satisfies state requirements and when the city can accept project closeout from regulators.
Board action and key approvals
- The board adopted a cost-saving change order with Coakley Cook Company Inc. for…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat