District installing dark fiber and classroom technology; fiber boring struck a fire riser that was repaired quickly
Summary
Forest Grove SD 15 staff described a district-wide dark-fiber project to increase bandwidth and redundancy and recounted an instance where boring for fiber struck a fire riser at the high school; facilities repaired the riser within days and work continued.
Get email alerts on the Technology Fiber topic
No spam. Unsubscribe anytime.
District staff reported progress on a dark-fiber loop that will connect district buildings and increase bandwidth capacity and redundancy. Staff said the dark-fiber loop work is largely underground and expected to be finished in July.
Staff said the benefit of district-owned fiber is the ability to increase capacity by swapping optics in network equipment without renegotiating circuit capacity with providers, and noted redundancy benefits if a cut occurs in one segment.
The presentation included a photo and description of a construction incident: during boring at Forest Grove High School, equipment struck a fire riser pipe. Staff said the facilities crew responded promptly, shut off water, coordinated repairs and restored the system within a couple of days. Staff noted the incident demonstrates the kinds of anomalies encountered in underground work and said the project remains on track.
Separately, staff reported classroom technology upgrades across the district will continue this summer, with the high school and other seismic-impacted rooms scheduled for phased work behind contractor activities.
No formal actions or votes were taken by the oversight committee because a quorum was not present; the description was provided as an informational update.