City says Civic Center demolition remains under budget after $540,100 change orders
Summary
Council discussed change orders to the Civic Center demolition contract with Sabre Demolition and city staff clarified that, despite increases, the demolition work remains about $1.8 million under the $8.15 million budgeted ceiling.
City staff told the council that change orders to the Civic Center demolition contract have raised the contractor’s contract value but that the demolition remains under the original $8.15 million budget.
Sam, City staff, said the original demolition budget was $8,150,000, the original contract award was about $4.3 million, and subsequent change orders have increased…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat