High school renovation moves into construction: natatorium demo, permits pending and phased schedule through 2029
Summary
Consultant CHA reported progress on the high school renovation: Planning Commission preliminary final approval, PECO equipment procurement, water-line conveyance documents executed, natatorium demo begun, AM radio tower demolition scheduled, and a phased renovation schedule stretching from 2026 through 2029.
CHA consultant Colin Case updated the North Penn School District Facilities and Operations Committee on May 27 on construction activity and schedule for the high school renovation project.
Case said the project received preliminary final approval from the Planning Commission and the team will appear before the Board of Supervisors the following night. PECO’s engineer has confirmed electrical equipment specifications and procurement is underway; legal documents for conveyance of water lines to the North Penn Water and Sewer Authority have been executed. Case reported that the general contractor has meter pits approved and the project is awaiting delivery dates.
Work in phase 1 has begun: selective demolition in the natatorium started May 20, temporary fencing and site mobilization are in…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat