Smyrna approves contract authorization for Windy Hill Boulevard construction oversight
Summary
Council authorized a contract not to exceed $336,840 with Corey Engineering to manage construction inspection and oversight for Windy Hill Boulevard through December 2025; funding is from SPLOST 2016.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The City of Smyrna authorized a contract to allow Corey Engineering to manage day-to-day construction and inspection work on the Windy Hill Boulevard project, approving a not-to-exceed amount of $336,840 to be funded from SPLOST 2016.
The agenda description identified the contractor and terms: “authorization to allow Corey Engineering of 200 Cobb Parkway North, Building 400, Suite 413, Marietta, Georgia, to manage the day to day construction and inspection of the Windy Hill Boulevard project through December 2025 in the amount not not to exceed $336,840 to be funded from SPLOST 2016,” and said the contract “will cover the cost of a senior professional to an structure manager to be accrued on an hourly basis.” The council discussed the item briefly and then took a motion.
The motion was moved by Ms. Rogalsby and seconded by Ms. Hines; the vote passed 4-0. No amendments, alternative vendors, or schedule changes were recorded in the meeting record. The contract term stated on the agenda extends through December 2025; the funding source was identified as SPLOST 2016. The council did not request further negotiation or return of the contract to a future meeting during the discussion recorded in the transcript.