Engineering report: Washington County reports paving miles, drainage repairs and $238,000 FEMA reimbursement

3628745 · June 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County Engineering Development Services told the court it completed large drainage projects in-house, advanced paving and culvert work, acquired crushed-concrete material for ongoing base purchases and reported a larger-than-expected FEMA reimbursement totaling about $238,000.

Washington County's Engineering Development Services (EDS) presented its quarterly operations report Tuesday, detailing road paving progress, drainage projects, vehicle and equipment updates, and federal reimbursements related to last year's storm response.

EDS said it processed 368 work orders during the quarter and issued 31 on-site sewage facility (OSSF) permits to date this year, slightly above last year's pace. The department reported 83 new addresses to date versus 56 at the same point last year and described multiple recent subdivisions and replats under review.

On road work and materials, EDS reported it has acquired 32,414 tons of base material through May and plans to use about 65,000 tons for the rest of the year, prioritizing crushed concrete for cost and access advantages. Paving progress for 2025 includes 4.23 miles completed and 3.53 miles scheduled for the coming week (Tonkawa, Indian Paintbrush and Chadwick Hogan). EDS also reported 69 driveway culverts installed year-to-date (driveway fee collections of $29,600) and multiple ongoing paving and repair projects in Chapel Hills and Valley Park.

EDS highlighted four large drainage projects that staff completed in-house after comparing contractor pricing; staff said contracting all work would have cost about $850,000 but county crews and rented equipment accomplished the work at substantial savings. "They did a phenomenal job," the department presenter said, identifying two crew leaders and praising staff proficiency on complex excavation and culvert work.

The department also said it had completed an urgent repair to Lomax Hormel Bridge after an inspection raised safety concerns and noted progress on bridge advanced-funding agreements (AFAs) with the state for several projects scheduled for 2026 and on design for Artesian Park and other projects.

On disaster reimbursements, EDS said initial estimates of about $160,000 were revised upward after state and federal review; Category A costs will be covered by state and federal funding and the county now expects roughly $238,000 in reimbursement, with $190,000 already received. EDS reported equipment-replacement progress, recent auction proceeds of $30,565 for old equipment, and an herbicide program focused on Johnson grass along road rights-of-way.

Commissioners praised staff for cost savings and delivery. EDS said the CDBG mitigation project for Myersville Road is at design kickoff and that the department will continue design, environmental review and outreach as the grant requires.

Why it matters: the report describes immediate county infrastructure work, dollars spent and reimbursed from disaster response, and material and manpower choices that affect road conditions and future county budgets.