Painesville Electric reports maintenance, distribution projects and AMI and transformer work
Summary
Department leaders updated council on plant testing, generator maintenance, distribution line repairs, a Richmond Road substation breaker replacement plan, vehicle procurements and AMI close‑out work; staff said some distribution faults will require wire replacement and possible bidding for contractor work.
Painesville Electric staff gave a departmental update to council on May 19 detailing recent plant tests, maintenance actions, distribution repairs and ongoing projects.
Highlights reported by staff: The power plant operated a successful generator test, followed by boiler cleaning and visual turbine inspections; staff reported a small leak discovered and scheduled contractor repairs. Distribution staff reported locating a fault between the plant and a downstream site and said they plan to replace all three legs…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat