Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Courthouse Construction topic

No spam. Unsubscribe anytime.

County receives courthouse construction update; approves change order, contingency at roughly $80,000

3622883 · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Pulaski County received a project update for the courthouse renovation, approved change order number 76 (roughly $14,000) and learned the current owners’ contingency stands at about $79,700; two larger recent change orders for plaster work and landscaping were discussed.

Pulaski County officials received a status update on the courthouse renovation project and approved change order number 76, which the presenter described as roughly $14,000. County staff reported the project owners’ contingency had fallen to approximately $79,700.

Nathan (Project Manager/Commissioner) reported that two change orders had been signed since the last meeting: a substantial plaster repair contract—described as “probably $40,000” for plaster replacement in portions of the courtroom ceiling—and a roughly $14,000 landscaping revision that had been handled administratively but should have come before the board. He said additional allowances in bids were expected to cover minor remaining changes and that most other anticipated expenses for IT, furniture and appliances remained uncertain.

The board voted to approve change order number 76. Staff noted the State Board of Accounts reporting considerations when approving the change order. Project milestones reported to commissioners included a punch-list walkthrough scheduled with Lumenat (contractor) for the basement and first floor, staining and clear-coating schedules for upstairs floors, pending protective coating for the north steps, and furniture delivery tentatively scheduled for the week of June 16. Staff also reported progress on meeting-room wallpaper, poured concrete sidewalks and ADA pads, and planned landscaping activity.

The presenter said the construction contingency was not large and that staff anticipated carving funds from other line items and the release of remaining balances later in the summer. The county will continue to track change orders and allowances and return to the board with additional approvals as needed.