Commissioners discussed a placeholder budget of $31,250 to match a potential Texas Water Development Board Flood Infrastructure Fund grant for a multimillion‑dollar drainage project along Highway 27 in CenterPoint.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
Kerr County commissioners on Monday discussed keeping a $31,250 placeholder in the flood fund to cover a 25% local match if a state flood‑infrastructure grant comes through for storm drainage work in the CenterPoint area along Highway 27.
Commission staff explained the county has submitted several projects to the Texas Water Development Board’s Flood Infrastructure Fund and that the CenterPoint project—drainage work to improve outlets under and downstream of Highway 27—ranked among the top 30 of more than 200 applicants. The County’s representative said the board is prioritizing the highest dollar projects first and is currently engaging with the top three or four.
“Before [a project] is construction ready, they want you to go through a very particular process and a cost benefit analysis,” the county project lead said, noting the $31,250 figure represents a 25% match on a $125,000 planning/engineering phase and would fund consultant work needed to advance the project to construction readiness.
The county also discussed a separate, longer‑term need for a countywide drainage master plan. Staff said they do not believe the master plan is immediately necessary but expect the county will need such planning within the next decade.
Commissioners did not approve the expenditure Monday but were asked whether to leave the placeholder in the budget. Staff said that if the county receives a direct request from the Water Development Board in the next six to eight months, having the budgeted match available would speed the grant process. If the board does not reach out to projects of this rank during the current cycle, the court can revisit the item next year.
Commissioners also discussed dam integrity evaluations for local impoundments such as Flat Rock/Ingram lake and noted that evaluations typically include core condition, valves and the ability to safely draw down an impoundment for repairs. Staff said some repairs — such as valve replacements — can require draining a lake and that experts routinely recommend evaluations to plan future capital work.
No formal vote was taken. Staff advised the court to consider whether to leave the $31,250 placeholder in the next fiscal budget or remove it and add it later if the county receives a clear call from the state.