Board approves $274,240 bid to rebuild north‑side sidewalk on Cormier Road; spot repairs planned on south side

3619411 · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees awarded the Cormier Road concrete sidewalk reconstruction contract to Aldex Construction for $274,240 to replace north‑side sidewalk from Shady to Ridge and to add spot repairs on the south side; project came in under the $329,000 budget.

The Village Board voted Tuesday to award the Cormier Road concrete sidewalk reconstruction project to Aldex (Al Dix) Construction for $274,240, covering full replacement of the north‑side sidewalk from Shady to Ridge and spot repairs on the south side.

Brian Rickert explained the project and bid alternatives presented to the board. "We did receive bids from Al Dix and Martell Construction. We are recommending to go with alternate b. Alternate b does include, essentially to replace all of the sidewalk on the North Side Of Cormier from Shady to Ridge," Rickert said.

Staff noted the project was included in the 2025 capital improvement plan and the recommended alternate brought the project in under the original budget of $329,000, allowing for additional south‑side spot repairs. The board approved the motion to accept Aldex Construction's bid by voice vote.

Trustees asked about contractor locality; staff said Aldex Concrete is based in Kaukauna and that village crews have worked with the contractor previously.

The project will proceed with the awarded contractor and staff will schedule construction per the capital plan.