Committee approves $169,842 change order and $20,008 deductive credit for Racquet Center hurricane repairs
Summary
Columbia County approved Change Order 6 for $169,842 and Change Order 7 (deductive) for $20,008 with Sherry Mutimer Construction to cover hurricane-related repairs and to credit remaining allowances for the Racquet Center project; staff said FEMA and insurance reimbursements are being pursued.
Get email alerts on the Racquet Center Repairs topic
No spam. Unsubscribe anytime.
The Columbia County Services Committee approved two change orders with Sherry Mutimer Construction related to hurricane damage at the Racquet Center.
Staff presented Change Order 6, a $169,842 additive change order that adds 106 days to the contractor’s timeline to cover repairs to fencing, courts, lights, tree wells, the pro shop roof and related cleanup resulting from hurricane damage. Staff said the county has been coordinating with insurance and FEMA reimbursement efforts and expects a portion of the costs to be reimbursed.
The committee also approved Change Order 7, a deductive change order of $20,008 that removes leftover contract allowances. Staff recommended both actions.
Committee members moved the items to consent and approved them. Staff noted the work was substantial and that reimbursement efforts with FEMA and insurance were ongoing; no individual vote tallies were recorded in the transcript.