Planning commission approves Kings Lake West preliminary plat, grants half‑street waiver amid infrastructure concerns
Summary
The City Planning Commission approved a master preliminary plat for Kings Lake West and granted a waiver allowing half‑street construction along County Road 43, after lengthy discussion about wastewater capacity, emergency access and future road buildout.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
The City Planning Commission on a majority vote approved the Kings Lake West master preliminary plat and separately granted a half‑street construction waiver for the County Road 43 frontage, allowing the developer to construct one side of the arterial section now and the other side later when adjacent property develops.
The waiver and the master preliminary plat were recommended by staff and the technical review committee. Commissioners debated the applications at length, weighing near‑term public‑safety and access concerns against the likelihood that full buildout and required wastewater improvements will follow.
Bria Whitmire, Development Services, explained the proposal: “the request is for a half street construction of the North South is, County Road 43” and described the planned cross section as a 27‑foot back‑to‑back curb with typical lane widths and a 5‑foot sidewalk. Whitmire told the commission the half‑street request meets Unified Development Code (UDC) criteria for a waiver and that staff recommends approval if it is not “detrimental to the public health.”
Commissioners pressed staff on safety and sequencing. “I am concerned that if King's Lake gets built out, and development on the West Side does not get, you know, I mean, who knows whenever that property is gonna get developed. So what do you do in the interim?” said Commissioner Miller. Commissioners also asked about striping, emergency vehicle turns, and whether the paved section being built now would later need wholesale reconstruction.
Beau Weishardt, consultant with Dave Dawson Engineers, said the applicant proposes to construct “half of an A‑2” arterial section with an arterial pavement structure underneath so the portion built now will carry heavy loads and not be a weak temporary pavement. “What we're requesting is half of an A‑2,” Weishardt said, and added that the proposed cross‑section is intended to minimize future deconstruction when the second half is added.
Commissioners and staff also discussed wastewater capacity and a separate City capital improvement project (CIP) to expand the Greenwood lift station. Staff said the CIP project is out for bid and that timing of lift‑station improvements has constrained development sequencing; the lift‑station expansion was described as the critical enabling project for additional final plats in the area. Staff described typical triggers in plats and public improvement plans that will require secondary access and fire‑code compliance as density increases.
After public comment from the project consultant and further discussion, Commissioner [unnamed motion maker] moved to approve the half‑street waiver as presented by staff; the motion was seconded and the commission approved the waiver. Later the commission approved the Kings Lake West master preliminary plat; the roll call included an opponent vote and at least one commissioner stating they were "not happy about it," but the motion passed.
Staff emphasized that this approval is for a master preliminary plat and does not authorize construction of lots; final plats, public improvement plans and fire, traffic and public‑works reviews remain required before building permits are issued. Whitmire and other staff said fire, solid waste and other departments will review the public improvement plans during subsequent preliminary and final review stages.
Commissioners who expressed concern suggested the UDC may need amendments to require perimeter/perimeter‑road buildout earlier in phased developments and to address fairness between early and later developers. Several speakers said impact fees or clearer UDC language could change developer incentives and the timing of infrastructure construction.
The commission recorded motions to approve the waiver and then the master preliminary plat; both motions passed. Additional conditions and technical reviews will be required during subsequent submittals for public improvement plans and final plats.