Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Logan Light & Power seeks $4 million from reserves to replace two 40‑year transformers; five‑year lead time warned
Summary
Mark, speaking for Light & Power, told the Logan City Council budget workshop that the utility needs $4,000,000 from reserves to replace two aging transformers at Substation 1 and that the units take about five years to manufacture.
Mark, speaking for Light & Power, told the Logan City Council budget workshop that the utility needs $4,000,000 from reserves to replace aged equipment at Substation 1, and that the units take about five years to build.
“We need $4,000,000 from reserves to replace, transformers up at Substation 1. That is the 1 up at Green the mouth of Green Canyon. And that is 1 of the 2 substations where we have our point of common coupling with Rocky Mount Power and we bring power into the city. K. Those transformers are pushing 40 years,” Mark said.
The request…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat

